GN SD 400 shield drilling mud system adapts with shield drilling cycling system. Its handling capacity can reach up 400m3/h.
SD 400 shield drilling mud system is composed of 3 classes solids control stages. The first stage
consists of GNZS83-3BF shale shaker for screening; the second and third stage consist of ZQJ300×3 desander , ZQJ125×18 desilter, 2 sets sand pump. The main working principle is using sand pump to supply sufficient power for the cyclone, then the drilling mud can enter the cyclone for centrifugal separating. The drilling mud has been refined.
Matching equipments of SD 400 shield drilling mud system:
1.ZG-17 mud recovering tank 1pc
2.FG-20 mud storage tank 1pc
3. GNZS83-3BF linear shale shaker 2set
4. ZQJ300×3 desander 1set
5.SB8×6-13sand pump 2set
6. JBQ mud agitator 2 set
7. SLH150-50 jet mud mixer 1 set
Main function of SD 400 shield drilling mud system
The mud recycling system's role in the process are: recycling, and refining drilling fluids with a great amount of cuttings (sediment) from the wellhead .this system can eliminate sands above 1.0mm in size, and supply drilling rigs with satisfied drilling fluids
The installation of SD 400 shield drilling mud system
Level off the work site, set a good base. As show as figure 1 : install and fix GNZS83-3BF shale shaker & ZQJ300 ×3 desander,ZQJ ZQJ125 ×18 desilter,SLH150-50jet mud mixer. Link all manifolds ,walkways, guardrails ,ladders, etc.. Ensure all parts flexible and on good condition. Connect mud tanks, het mud mixer, and the up& down manifolds. Connect all the solids control equipment control circuit connectors. Connectors for jet mud mixer is linked by air connectors with electric panel 2. 
Maintenance of SD 400 shield drilling mud system
All equipments on the tank should keep clean while used. All sand, water of the tanks should be piped out. Let out mud of sand pumps,pipes,educators.
Be careful to the quality of equipments while transportation.
The electric panels should be maintained specially. The illustrations are attached as followed. There are illustrations in every electric panel as well.
For more details of GN SD 400 shield drilling mud system, please feel free to contact GN.